- Question 1Advanced
PRINCE2 Principles · Learn from Experience
A Project Manager diligently creates a Lessons Log during the project but fails to produce a Lessons Report at the end of each stage. What is the most likely negative consequence of this omission for the current project?
Show answer & explanation
Correct answer: C
The 'Learn from experience' principle is a continual activity. While the Lessons Log captures lessons, the Lessons Report analyzes and summarizes them for review at key points, like the end of a stage. Failing to create and review this report means that lessons from one stage are not formally considered when planning the next, making it likely that mistakes will be repeated within the same project.
- Question 2Beginner
People · Stakeholder Engagement
True or False: In a PRINCE2 project, the Project Manager is solely responsible for all communication with every stakeholder.
Show answer & explanation
Correct answer: B
False. While the Project Manager has a significant communication role, they are not solely responsible. The Communication Management Approach defines the communication needs of all stakeholders. Other roles, such as the Executive, Senior User, and Team Managers, also have specific communication responsibilities with different stakeholder groups.
- Question 3Intermediate
PRINCE2 Principles · Define Roles, Responsibilities and Relationships
A consultant reviews a project's organization structure and notes that the individual in the Project Assurance role reports directly to the Project Manager. Which PRINCE2 principle is being violated?
graph TD PB["Project Board"] --> PM["Project Manager"]; PM --> PA["Project Assurance"]; PM --> TM["Team Manager"];Show answer & explanation
Correct answer: D
This principle is violated. Project Assurance is the responsibility of the Project Board and must be independent of the Project Manager. This ensures objective monitoring and reporting on the project's performance. If Project Assurance reports to the Project Manager, this independence is lost, creating a conflict of interest.
- Question 4Beginner
Key Concepts · Project Performance
PRINCE2 7 introduced 'sustainability' as one of the seven aspects of project performance to be managed. What does this primarily refer to?
Show answer & explanation
Correct answer: C
The sustainability performance target refers to the project's impact on environmental and social factors. PRINCE2 7 encourages projects to consider their wider footprint and to make decisions that are not only economically viable but also environmentally and socially responsible.
- Question 5Intermediate
People · Team Management
A project team is experiencing frequent arguments and a lack of trust, which is impacting progress. According to the PRINCE2 7 'People' element, what is the most appropriate first step for the Project Manager?
Show answer & explanation
Correct answer: C
The 'People' element emphasizes understanding individuals and how they work together. Before taking drastic action, the Project Manager should first seek to understand the root cause of the conflict by analyzing the team's dynamics, individual motivations, and communication styles. This understanding is crucial for effective leadership and conflict resolution.
- Question 6Advanced
PRINCE2 Practices · Business Case Practice
A project to build a new factory has a strong initial Business Case based on a 5-year financial forecast. Six months into construction, a new environmental regulation is passed that will require a costly filtration system, significantly increasing operational costs and reducing the project's net benefit. The project is still forecast to be profitable, but only just.
What is the correct action for the Project Manager in this situation?
Show answer & explanation
Correct answer: B
The principle of 'Continued business justification' requires that the Business Case is kept under review. The new regulation is an 'issue' that impacts the project's viability. The Project Manager must update the Business Case to reflect the new reality. Because this change significantly impacts the justification (a key tolerance), it constitutes an exception. An Exception Report must be sent to the Project Board, who will then decide whether the (now weaker) justification is still sufficient to continue.
- Question 7Intermediate
PRINCE2 Practices · Quality Practice
In the context of the PRINCE2 Quality practice, what is the fundamental difference between 'Project Assurance' and 'Quality Assurance'?
Show answer & explanation
Correct answer: C
This is the key distinction. Project Assurance is the Project Board's responsibility to assure itself that the project is being conducted correctly. It is part of the project's governance. Quality Assurance is an independent function that checks if the organization's quality management system is being followed. It operates outside the project team, often at a corporate or programme level.
- Question 8AdvancedSelect 3
PRINCE2 Practices · Organizing Practice
A small project has combined the roles of Executive and Senior User into a single individual to streamline decision-making. Which THREE of the following are potential risks of this tailoring decision? (Select THREE).
Show answer & explanation
Correct answers: A, C, F
The Executive is responsible for the Business Case, while the Senior User represents user needs. Combining them can lead to a bias where user wants are prioritized even if they threaten the project's value proposition.
The Senior User role may represent multiple user constituencies. If the combined role is held by a person from only one of those groups, others may be underrepresented.
This represents the core conflict. The Executive must balance cost, risk, and benefit, while the Senior User is focused on ensuring the product is fit for purpose. One person holding both roles creates an internal conflict between these two perspectives.
- Question 9Intermediate
PRINCE2 Practices · Quality Practice
A draft Project Product Description has been written, but the Project Manager notices that the 'acceptance criteria' section is empty. What is the most significant and immediate risk this poses to the
Closing a Projectprocess?Show answer & explanation
Correct answer: B
Acceptance criteria define the measurable conditions that must be met for the final project product to be accepted by the key stakeholders (usually the Senior User). Without these criteria defined and agreed upon upfront, there is no objective basis for accepting the product at the end of the project. This can lead to disputes and prevent the project from closing successfully.
- Question 10Beginner
PRINCE2 Practices · Business Case Practice
Within the PRINCE2 project management team structure, who holds the ultimate accountability for the project's success and the validity of its Business Case?
Show answer & explanation
Correct answer: C
The Executive is the chair of the Project Board and is ultimately responsible for the project. This includes securing funding and ensuring that the project remains viable, delivers value for money, and aligns with corporate strategy. The Executive owns the Business Case.