C-S43-2023 Sample Questions & Answers
Breakdown maintenance and work clearance make up the biggest share, alongside equipment and location records, task lists and refurbishment, planning preventive upkeep with meters and counters, Fiori apps for assets, org structure basics, and clean core principles.
Launch the full C-S43-2023 simulator →Showing 10 of 20 free samples.
- Question 1Advanced
Preventive Maintenance · Maintenance Strategies and Plans
Case Study: AeroComponent Manufacturing Inc.
AeroComponent Manufacturing Inc. produces high-precision turbine blades. They utilize a complex, high-value CNC milling machine that is critical to their production line. The machine requires regular, multi-faceted preventive maintenance. The maintenance plan must incorporate different cycles based on both time and machine usage.
Maintenance Requirements:
- A basic visual inspection and lubrication must occur every 30 days.
- A more detailed calibration check is required after every 500 hours of machine operation.
- A major overhaul, including the replacement of specific wear parts, is scheduled every 2 years or 8000 operating hours, whichever comes first.
System Configuration:
The SAP S/4HANA system has a performance-based counter set up to track the machine's operating hours. The maintenance department wants to manage all these requirements within a single, consolidated maintenance plan for simplicity and better oversight.Question:
Which type of maintenance plan and strategy should the SAP consultant configure to meet all of AeroComponent's requirements for the CNC machine?Show answer & explanation
Correct answer: B
A strategy-based plan is the correct solution for managing multiple, different maintenance cycles for a single technical object. The consultant would define a maintenance strategy with three separate maintenance packages: one time-based (30 days), one performance-based (500 hours), and a third that combines both time and performance triggers (2 years or 8000 hours). This consolidates all requirements into one plan, providing the desired simplicity and oversight.
- Question 2IntermediateSelect 3
Maintenance Processing - Advanced Functions · General Task Lists
A maintenance supervisor at a food processing plant is creating a general task list for the routine cleaning of a bottling line. This procedure involves several distinct steps, requires specific cleaning agents (materials), and must be performed by a certified sanitation team (work center). Which elements can be defined directly within the operations of this general task list? (Select THREE)
Show answer & explanation
Correct answers: A, C, E
- Question 3Beginner
Maintenance Processing - Basic Functions · Maintenance Order Creation
True or False: In SAP S/4HANA Asset Management, it is mandatory to create a maintenance notification before a maintenance order can be created for breakdown maintenance.
Show answer & explanation
Correct answer: B
While it is a common and recommended practice to create a notification first to document a malfunction, SAP S/4HANA allows for the direct creation of a maintenance order without a preceding notification. A notification can also be generated automatically from the order if configured.
- Question 4Intermediate
Managing Clean Core · Clean Core Violations
A company is migrating from SAP ERP 6.0 to SAP S/4HANA Cloud, Private Edition. The project lead insists on replicating a heavily customized report for maintenance costs using a custom ABAP program directly in the S/4HANA core. Why does this approach violate the 'Clean Core' principle?
Show answer & explanation
Correct answer: B
The 'Clean Core' principle aims to keep the core SAP system as standard as possible to ensure smooth, rapid upgrades and lower total cost of ownership. Building custom reports directly in the core using classic ABAP is a legacy approach. The modern, Clean Core-compliant method would be to use standard Fiori apps, CDS views, or build the report as a side-by-side application on SAP BTP.
- Question 5IntermediateSelect 2
User Interface and User Experience · Mobile Maintenance Apps
A field technician is using a mobile device to perform maintenance tasks at a remote wind turbine farm with intermittent network connectivity. Which features of modern SAP Fiori mobile apps for Asset Management are essential for this scenario? (Select TWO)
Show answer & explanation
Correct answers: A, C
- Question 6Beginner
Organizational Units and Master Data · Work Center Configuration
An administrator is setting up a new work center for a team of electricians. To enable capacity planning and scheduling for maintenance orders, which of the following must be maintained in the work center master data?
Show answer & explanation
Correct answer: B
Capacity planning requires the system to know how to calculate the required capacity (work). This is achieved by assigning a standard value key (e.g., for setup, machine time, labor time) and defining formulas in the work center's capacity header to calculate the capacity requirements based on the planned work in the maintenance order operation.
- Question 7Intermediate
Technical Objects · Equipment and Serial Number Management
When an equipment master record is created with serial number management, what is the relationship between the equipment master and the material master?
Show answer & explanation
Correct answer: B
This describes the core concept. A material master (e.g., 'Electric Motor 5kW') defines the general characteristics of an item. A serial number profile is assigned to this material. When a specific instance of this motor is created (e.g., 'Serial Number 12345'), an equipment master record is automatically or manually created to track that individual object throughout its lifecycle.
- Question 8Advanced
Maintenance Processing - Advanced Functions · Refurbishment Processing
Case Study: Global Logistics Corp (GLC)
GLC operates a massive fleet of delivery trucks. To improve maintenance efficiency and asset utilization, they are implementing the refurbishment process in SAP S/4HANA for high-value components like engines and transmissions.
Current Process:
When a truck's engine fails, it is removed and replaced with a new one from inventory. The faulty engine is then sent to a third-party vendor for repair and returned to GLC's warehouse as a refurbished, serviceable unit. The maintenance planner is struggling to track the value and status of the faulty engine throughout this process.Goal:
Implement a standard SAP process to manage the engine refurbishment. The process must correctly handle the valuation of the engine as it moves from a 'faulty' state to a 'refurbished' state and ensure costs are tracked accurately.Question:
Which sequence of steps correctly represents the standard SAP refurbishment order process for GLC's engine?sequenceDiagram participant Planner participant Warehouse participant System participant Finance Planner->>System: Create Refurbishment Order (IW81) Warehouse->>System: Goods Issue of Faulty Engine Note over System: Engine value transferred to Order Planner->>System: Record Repair Costs (Labor/Parts) Warehouse->>System: Goods Receipt of Refurbished Engine Note over System: Refurbished Engine value updated Planner->>System: Settle Order Costs System->>Finance: Post Financial EntriesShow answer & explanation
Correct answer: B
This is the standard SAP refurbishment process flow. A specific order type is used for refurbishment. The faulty material is issued from stock to the order, which transfers its value to the order. Repair costs (labor, parts, services) are posted to the order. Finally, a goods receipt is performed to bring the refurbished material back into stock, typically at an updated value that includes the repair costs.
- Question 9Advanced
Preventive Maintenance · Measuring Points and Counters
A maintenance plan for a critical production conveyor is based on a performance counter that tracks meters of material transported. The counter has a defined maximum value (overflow reading) of 999,999 meters. The system administrator notices that after the counter passed this value and reset to zero, the maintenance plan did not trigger a new maintenance order as expected. What is the most likely configuration issue?
Show answer & explanation
Correct answer: B
For a performance-based maintenance plan to correctly calculate the next due date after a counter resets (overflows), the 'Counter Overflow' indicator must be set in the measuring point's master data. This tells the system that when a new reading is lower than the previous one, it should add the overflow value to its calculation, ensuring the plan continues to schedule correctly.
- Question 10Intermediate
Maintenance Processing - Advanced Functions · Task List Usage
True or False: Once a task list is copied into a maintenance order, any subsequent changes made to the master task list are automatically reflected in that existing maintenance order.
Show answer & explanation
Correct answer: B
When a task list is assigned to a maintenance order, its operations, materials, and other data are copied into the order at that point in time. The order then becomes a standalone transactional document. Any changes to the original master task list after this point will not affect the order that has already been created. This ensures the integrity of the work plan for that specific job.