PSM II Sample Questions & Answers
Scrum theory and team dynamics tie with facilitation, coaching and mentoring for the biggest share, alongside evolving the wider organization, managing the product backlog and stakeholders, and building in technical excellence and continuous delivery.
Launch the full PSM II simulator →Showing 10 of 20 free samples.
- Question 1Select 3
At the end of the eighth Sprint, the internal sponsors are upset and angry with the progress of the product being built. The current state of the product is not as expected and will require additional Sprints and more budget than originally anticipated at the start of the project.
What factors may have led to this? (Choose three.)
Show answer & explanation
Correct answers: A, B, E
A, B, E -- Explanation:
One of the principles of agility includes working closely with business people. In order to manage stakeholder expectation, there must be open communication (through collaboration and transparency) throughout the project cycle. This maximizes alignment, helps with making business decisions, and reduces risk.
Although, the Scrum Guide does not directly state that the Scrum Master is responsible for ensuring transparency it is implicit. The Scrum Master is responsible for the process in which Scrum is adopted and enacted. Scrum is founded on empiricism and the Scrum Master helps those inside and outside the team work in an empirical environment which includes transparency (one of the three pillars of empiricism).A, B, E -- Explanation:
One of the principles of agility includes working closely with business people. In order to manage stakeholder expectation, there must be open communication (through collaboration and transparency) throughout the project cycle. This maximizes alignment, helps with making business decisions, and reduces risk.
Although, the Scrum Guide does not directly state that the Scrum Master is responsible for ensuring transparency it is implicit. The Scrum Master is responsible for the process in which Scrum is adopted and enacted. Scrum is founded on empiricism and the Scrum Master helps those inside and outside the team work in an empirical environment which includes transparency (one of the three pillars of empiricism).A, B, E -- Explanation:
One of the principles of agility includes working closely with business people. In order to manage stakeholder expectation, there must be open communication (through collaboration and transparency) throughout the project cycle. This maximizes alignment, helps with making business decisions, and reduces risk.
Although, the Scrum Guide does not directly state that the Scrum Master is responsible for ensuring transparency it is implicit. The Scrum Master is responsible for the process in which Scrum is adopted and enacted. Scrum is founded on empiricism and the Scrum Master helps those inside and outside the team work in an empirical environment which includes transparency (one of the three pillars of empiricism). - Question 2
Three Development Teams are currently building a single product and pulling work from the same Product Backlog. All three teams have identified that they will need Dan, a database specialist, to work full time in their team for the next several Sprints.
What should Steven, the Scrum Master, do to solve this potential problem?
Show answer & explanation
Correct answer: C
Explanation:
As a servant/leader, the Scrum Master facilitates conversations through open ended questions in order to help the team members make the best possible decisions according to what is known at the time. He/she does not approve or reject team decisions but ensures the team stays within the boundaries of the Scrum framework. - Question 3Select 2
Because the Development Team is the ones doing the work, they are best suited to inspect and adapt the progress toward the Sprint Goal. At minimum, this is done every 24 hours through the Daily Scrum. It is the Scrum Master’s responsibility to teach the Scrum Team the value and objective of each Scrum event in order for them to optimize the benefits of each event. Because the Daily Scrum is owned by the Development Team, it is up to them on how they should run it but the Scrum Master can provide guidance to ensure it adheres to the Scrum guidelines.
Which two things should Steven first advise? (Choose two.)
Show answer & explanation
Correct answers: B, D
B, D -- Explanation:
The Scrum Master serves the organization in several ways, including: Leading and coaching the organization in its Scrum adoption; Planning Scrum implementations within the organization; Helping employees and stakeholders understand and enact Scrum and empirical product development.B, D -- Explanation:
The Scrum Master serves the organization in several ways, including: Leading and coaching the organization in its Scrum adoption; Planning Scrum implementations within the organization; Helping employees and stakeholders understand and enact Scrum and empirical product development. - Question 4Select 3
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
Show answer & explanation
Correct answers: A, B, C
A, B, C -- Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint Goal. Every day, the Development Team should understand how it intends to work together as a self-organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.A, B, C -- Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint Goal. Every day, the Development Team should understand how it intends to work together as a self-organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.A, B, C -- Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint Goal. Every day, the Development Team should understand how it intends to work together as a self-organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course. - Question 5
Steven is a Scrum Master asked to assist in creating five new Scrum Teams that will be working to build a highly anticipated product. He talks with them about the importance of being able to integrate their Increments by the end of their Sprints. This includes the first Sprints. The product is very important to both the end users and the organization.
Of the choices raised by future team members, what would Steven encourage?
Show answer & explanation
Correct answer: C
Explanation:
When a Product Backlog item or an Increment is described as “Done”, everyone must understand what “Done” means. If there are multiple Scrum Teams working on the system or product release, the Development Teams on all the Scrum Teams must mutually define the definition of “Done” to have a shared understanding of what it means for work to be complete, to ensure transparency.
Each Increment is additive to all prior Increments and thoroughly tested, ensuring that all Increments work together. - Question 6
According to the values of Scrum, which is the best way to create Development Teams?
Show answer & explanation
Correct answer: C
Explanation:
When the values of commitment, courage, focus, openness and respect are embodied and lived by the Scrum Team, the Scrum pillars of transparency, inspection, and adaptation come to life and build trust for everyone and self- organizing teams will be enabled to choose how best to accomplish their work. - Question 7
When multiple Scrum Teams are working from the same Product Backlog, also known as scaled Scrum, they must still work in conformance of the Scrum guide.
Show answer & explanation
Correct answer: A
Explanation:
Scrum is a framework with built in flexibility to support multiple Scrum Teams working on a single product. - Question 8Select 2
In Scrum, how would budgeting and financial forecasting be performed? (Choose two.)
Show answer & explanation
Correct answers: A, B
A, B -- Explanation:
The cost of developing, delivering, and sustaining products can impact how the flow of value is managed throughout the life of a product. Each Sprint is an opportunity to inspect the investment (financial, time, effort, etc.) against the returned value (customer satisfaction, revenue, etc.) of the work that has been delivered. The team can then decide on what it should do next to maximize the value of the investment.A, B -- Explanation:
The cost of developing, delivering, and sustaining products can impact how the flow of value is managed throughout the life of a product. Each Sprint is an opportunity to inspect the investment (financial, time, effort, etc.) against the returned value (customer satisfaction, revenue, etc.) of the work that has been delivered. The team can then decide on what it should do next to maximize the value of the investment. - Question 9Select 3
Steven is a Scrum Master that was hired to help an organization, that is new to Scrum, understands and enacts Scrum effectively.
Which three activities would be acceptable? (Choose three.)
Show answer & explanation
Correct answers: B, C, E
B, C, E -- Explanation:
The Scrum Master serves the organization in several ways, including: Leading and coaching the organization in its Scrum adoption; Planning Scrum implementations within the organization; Helping employees and stakeholders understand and enact Scrum and empirical product development.B, C, E -- Explanation:
The Scrum Master serves the organization in several ways, including: Leading and coaching the organization in its Scrum adoption; Planning Scrum implementations within the organization; Helping employees and stakeholders understand and enact Scrum and empirical product development.B, C, E -- Explanation:
The Scrum Master serves the organization in several ways, including: Leading and coaching the organization in its Scrum adoption; Planning Scrum implementations within the organization; Helping employees and stakeholders understand and enact Scrum and empirical product development. - Question 10
A Scrum Team has been working on a product for several iterations and has an average velocity of 55 units of ‘done’ work per Sprint. A second team will be added to work on the same product.
What might be the impact on the original team?
Show answer & explanation
Correct answer: B
Explanation:
Similar to membership changes within a single Scrum Team, adding or removing additional Scrum Teams working on the same product will impact productivity in the short term. Adding additional teams often go through recognizable stages as they change from being a collection of strangers to a united group with common goals. Bruce Tuckman's Forming, Storming, Norming, and Performing model describes these stages.