LEED-GA Sample Questions

LEED-GA Sample Questions & Answers

How LEED rating systems are organized and scoped carries the most weight, next to integrative design thinking, site selection and transportation, sustainable sites, efficient water and energy use, sustainable materials, indoor air quality, and project outreach.

Launch the full LEED-GA simulator →

Showing 10 of 20 free samples.

  1. Question 1Beginner

    Location and Transportation · Reduced Parking Footprint

    A project is located in a dense urban center with excellent access to public transportation, including multiple bus lines and a subway station within a 1/4-mile walk. The developer wants to minimize parking to reduce costs and encourage sustainable transit. Which strategy would earn points in the Location and Transportation category for this project?

    Show answer & explanation

    Correct answer: B

    The goal of the Reduced Parking Footprint credit is to minimize the environmental harms associated with parking, including land consumption and encouraging driving. Providing no new parking is the highest-achieving strategy for this credit. Exceeding zoning requirements is the opposite of the credit's intent. Providing preferred parking is a separate credit (Green Vehicles). Providing only the minimum required parking is a good first step but providing no new parking is a specific strategy that earns the most points.

  2. Question 2Beginner

    LEED Process · Organization Fundamentals

    What is the primary role of the Green Business Certification Inc. (GBCI) in the LEED certification process?

    Show answer & explanation

    Correct answer: B

    A key distinction to understand is the separate roles of the USGBC and GBCI. The USGBC (U.S. Green Building Council) is responsible for developing the LEED rating systems. The GBCI (Green Business Certification Inc.) was established to provide independent, third-party administration of the certification and credentialing processes. This includes reviewing project submissions and administering exams like the LEED Green Associate.

  3. Question 3Intermediate

    Indoor Environmental Quality · IAQ Management During Construction

    During construction of a new office building, the general contractor is responsible for implementing the construction IAQ management plan. According to SMACNA guidelines, which of the following actions is critical to protecting the HVAC system before occupancy?

    Show answer & explanation

    Correct answer: B

    The Sheet Metal and Air Conditioning National Contractors Association (SMACNA) guidelines for construction IAQ emphasize protecting the HVAC system from contamination. The most critical action is to seal all ductwork openings and equipment to prevent dust, debris, and moisture from entering the system during construction. Running the system can draw contaminants in. Using MERV 8 filters is a requirement, but it's done after the system is protected during construction and before occupancy. Cleaning ducts is a remedial action, whereas sealing them is a preventative one.

  4. Question 4IntermediateSelect 4

    Materials and Resources · Life-Cycle Thinking

    A project team is performing a life-cycle cost analysis (LCCA) for the building's exterior lighting. Which of the following costs should be included in the analysis? (Select ALL that apply)

    Show answer & explanation

    Correct answers: A, B, D, E

    A life-cycle cost analysis (LCCA) considers all costs associated with a product or system from 'cradle to grave'. This includes the initial purchase and installation costs (A), ongoing operational costs like energy (B), maintenance and replacement costs (D), and end-of-life disposal or salvage costs (E). Subjective values like marketing appeal (C) are typically not included in a standard LCCA.

  5. Question 5Beginner

    Project Surroundings and Public Outreach · LEED Accredited Professional

    A project team is pursuing the Innovation credit for having a LEED Accredited Professional on the team. To earn this point, the LEED AP must be a principal participant on the project. Which of the following roles would MOST likely qualify?

    Show answer & explanation

    Correct answer: C

    To earn the LEED AP credit, the accredited professional must be a 'principal participant' involved in the project from an early stage and throughout the process. The project architect who is involved from design through construction is a core team member and clearly qualifies. The other roles represent minimal or late-stage involvement and would not meet the intent of the credit, which is to have LEED expertise integrated into the project's decision-making process.

  6. Question 6Beginner

    Energy and Atmosphere · Energy Performance

    A project is using an energy model to demonstrate a 12% improvement in energy performance compared to the baseline building performance rating. What is the standard used to determine the baseline in LEED v4?

    Show answer & explanation

    Correct answer: C

    For the Energy and Atmosphere category, LEED v4 uses ASHRAE Standard 90.1-2010, Energy Standard for Buildings Except Low-Rise Residential Buildings, as the baseline for energy performance. Projects must demonstrate a percentage improvement over this baseline. ASHRAE 55 deals with thermal comfort, and ASHRAE 62.1 deals with ventilation and indoor air quality.

  7. Question 7Intermediate

    LEED Process · Rating System Selection

    A university is building a new science laboratory. The building design includes high-efficiency fume hoods, specialized process equipment, and extensive HVAC systems to maintain specific temperature and humidity levels for experiments. When selecting a LEED rating system, which factor is most critical in determining the appropriate choice?

    Show answer & explanation

    Correct answer: B

    The LEED rating system selection is primarily determined by the building's use type and the scope of work. The '40/60 rule' is used to choose the most appropriate rating system when a project could fit into multiple systems. This rule is based on the percentage of the gross floor area dedicated to a particular use. For a science lab on a campus, the team would need to determine if it best fits under LEED BD+C: New Construction or the more specific LEED BD+C: Schools, based on its function and the percentage of space used for K-12 or lab purposes.

  8. Question 8Advanced

    Integrative Strategies · Case Study Analysis

    Case Study:

    A development team is planning a 5-story, 100,000 sq. ft. mixed-use project in a downtown area on a previously developed site. The ground floor will be retail, with four floors of office space above. The project has a very tight budget and an aggressive schedule. The owner is committed to LEED certification but wants to prioritize strategies that have a clear return on investment and can be implemented without significant design changes at this late stage (schematic design is complete).

    The site is adjacent to a public park, has access to three bus lines, and is surrounded by a variety of services. The initial design includes a conventional roof, standard plumbing fixtures, and a large underground parking garage as required by local code. The team has identified that the local region's priority credits are focused on stormwater management and energy performance.

    Given the project constraints and goals, which two strategies should a LEED Green Associate recommend the team pursue first to maximize points with a strong ROI and address regional priorities?

    Show answer & explanation

    Correct answer: C

    This choice represents the best balance of cost-effectiveness, ROI, and alignment with regional priorities. Fundamental commissioning (an EA prerequisite) has a proven fast payback by ensuring energy systems run efficiently, addressing the energy performance regional priority. Specifying WaterSense fixtures (a WE prerequisite and credit) is a low-cost strategy that provides significant water and sewer cost savings with a very quick ROI. Both can be implemented late in the design process without major changes. The other options involve high initial costs (blackwater, renewables, passive house) or significant redesign efforts that conflict with the project's stated constraints.

  9. Question 9IntermediateSelect 2

    Location and Transportation · Surrounding Density and Diverse Uses

    A project team is trying to earn a point for Surrounding Density and Diverse Uses. The project is located in an area with a residential density of 15 dwelling units per acre. To earn the credit, the project must be within a 1/2-mile walking distance of a minimum number of 'diverse uses'. Which of the following would count as diverse uses according to LEED definitions? (Select TWO)

    Show answer & explanation

    Correct answers: A, C

    LEED defines diverse uses as services that meet daily needs and reduce car trips. A supermarket (A) and a public library (C) are classic examples that fall into distinct categories (Food Retail, Community/Civic Facility). Multiple instances of the same use type, like ATMs (B) or gas stations, only count as one use. A gated park (D) does not count because it is not publicly accessible at all times.

  10. Question 10Beginner

    Materials and Resources · Recycled Content

    Which of the following describes post-consumer recycled content?

    Show answer & explanation

    Correct answer: B

    Post-consumer content is material that has served its intended use and has been discarded by a consumer. Plastic soda bottles that have been used and recycled are a perfect example. Pre-consumer (or post-industrial) content is waste diverted from the landfill during the manufacturing process, such as sawdust from a mill, fly ash from coal production, or scraps from a factory.

Ready for the real thing?