CAP Sample Questions

CAP Sample Questions & Answers

Free Certified Authorization Professional practice questions with worked answers and explanations. See how the ExamJungle simulator prepares you — then jump into the full test.

Launch the full CAP simulator →

Showing 10 of 20 free samples.

  1. Question 1

    You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast track the project work to get the project done faster.

    When you fast track the project which of the following are likely to increase?

    Show answer & explanation

    Correct answer: D

    D

  2. Question 2Select 4

    What NIACAP certification levels are recommended by the certifier?
    Each correct answer represents a complete solution. Choose all that apply.

    Show answer & explanation

    Correct answers: A, C, D, E

    A,C,D,E

    A,C,D,E

    A,C,D,E

    A,C,D,E

  3. Question 3

    Which of the following is used to indicate that the software has met a defined quality level and is ready for mass distribution either by electronic means or by physical media?

    Show answer & explanation

    Correct answer: C

    C

  4. Question 4

    Which of the following statements about role-based access control (RBAC) model is true?

    Show answer & explanation

    Correct answer: A

    A

  5. Question 5

    Mary is the project manager of the HGH Project for her company. She and her project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor.

    What type of a response strategy is this?

    Show answer & explanation

    Correct answer: B

    B

  6. Question 6

    Which of the following processes is used to protect the data based on its secrecy, sensitivity, or confidentiality?

    Show answer & explanation

    Correct answer: A

    A

  7. Question 7

    Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you.

    What component of the change control system communicates the approval or denial of a proposed change request?

    Show answer & explanation

    Correct answer: C

    C

  8. Question 8

    In what portion of a project are risk and opportunities greatest and require intense planning and anticipation of risk events?

    Show answer & explanation

    Correct answer: A

    A

  9. Question 9

    Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders - including management.

    Mark will need to update all of the following information except for which one?

    Show answer & explanation

    Correct answer: A

    A

  10. Question 10

    What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?

    Show answer & explanation

    Correct answer: B

    B

Ready for the real thing?

The full CAP simulator has every exam-style question, timed mode, and instant scoring.

Go to the CAP simulator →